TM 55-2210-224-34
3-29. LOAD METER SHUNT (cont)
TEST
9. Use a multimeter and perform a continuity test on the load meter shunt. Replace defective unit.
INSTALLATION
10. Position shunt base (19) and install four flat washers (18), lockwashers (17), and nuts (16).
11. Install six flat washers (15), two nuts (14), and flat washers (13). Install shunt (12) on shunt base (19).
12. Install two flat washers (11), lockwashers (10), nuts (9), and flat washers (8) on shunt (12). Connect two wires (7)
and install two flat washers (6), lockwashers (5), and nuts (4). Remove tags.
13. Connect two wires (3) and install spacer (2) and two nuts (1). Remove tags.
14. Close electrical equipment cabinet door.
3-126